The calculation of the deemed export is based on the following factors and has been set by the CRU.
Deemed Export Quantity= MEC x Capacity Factor x Export Factor x Provision Interval
MEC – This will come from the NC6 form which the customer is required to submit to ESBN.
Capacity Factor – This is based on a calculation from the CRU and is set at 9.7%
Export Factor – This is based on a calculation from the CRU and is set at 35%
Provisional interval – This is a calculation used for solar installations that takes account of how Microgeneration works in practice during the day and from season to season.
It’s important to note that as customers transition towards eligibility for a smart meter, they will also move towards actual export data.